The city is all set to not only revive the dysfunctional biomethanisation plants but is also set to get four new plants with the same technology. There are 13 biomethanisation plants in the city each with five Tonnes Per Day (TPD) capacity, of which presently only three are partially running.
Bengaluru Solid Waste Management Ltd. (BSWML) has now taken up a project to revive seven of the dysfunctional plants at a cost of ₹4.5 crore. It will also upgrade the remaining six in the second phase. Meanwhile, the company has also taken up a project to install four new Bio-CNG plants in Basavanagudi, Kogilu, Byatarayanapura, and Mahadevapura at a cost of ₹10 crore.
“Ten of the 13 existing plants have been dysfunctional for a long time now. Moreover, these plants need an update of technology as well, which we are carrying out now. The four new plants will also come up soon,” said Basavaraj Khabade, MD, BSWML.