Railway have completed the electrification of the 65.12-km line between Shoranur and Nilambur. The inspection run along the section was carried out successfully on Saturday.
Railway officials said the project using 25 kv, 50 hz AC single-phase power was one of the major development achievements of the Palakkad Railway Division.
Southern Railway’s Principal Chief Electrical Engineer A. K. Siddhartha, Chief Project Director of Railway Electrification Sameer Dighe, Additional Divisional Railway Manager S. Jayakrishanan, Senior Divisional Electrical Engineer Sandeep Joseph, and several other senior officers were among the team that conducted the trial run.