The EU proposed the Cloud and AI Development Act, creating "acceleration zones" in each member state with a 12-month permitting ceiling. Projects meeting two of five criteria could gain "strategic" status. The act is still a proposal, and the 12 months cover the permit only, not construction or grid connection.
On the environment, measurement comes first. Data centres with at least 500 kilowatts of IT power must report annual energy and water use. In September, the Commission adopted an A-to-G efficiency label, with the first ratings due in August 2027. But a label is not a limit: it grades performance without forcing any data centre to reach a certain grade. A consultation on binding minimum standards runs until 14 December, with a proposal planned for 2027.