Major roadworks on Glasgow's M8 have been delayed once again and will not be complete until the end of 2024.
It has now been confirmed that the Woodside Viaduct slip road at Charing Cross is likely to remain shut until late 2024, despite a previous estimated end date of November 2023.
Amey, who are undertaking the project on behalf of Transport Scotland, said the delays are due to "bespoke propping designs and solutions" required for the works.