The construction of HS2’s physical structures should have been “largely completed” by now under the project’s initial timeline – but it is actually just over halfway there, the project’s chief executive has admitted.
HS2 Ltd chief executive Mark Wild blamed major delays in the execution of the project on “inefficiency of work” as a result of the decision to start construction work before the finalised design or consents were in place.