People living in Johnstone will see a huge investment in their area after Scottish Gas Networks announced that £211,000 will be spent on improvements.
The works will happen in three stages, with approval coming from the Renfrewshire Council, and start on Tuesday, September 20 for 12 weeks.
Phase 1 will take around three weeks from Tuesday, September 20 and involves the closure of a section of the B789 Barrochan Road from its junction with Sandholes Road, to approximately 50 metres south of Magnus Road. During this time a signed diversion route will be in place for motorists via Fulton Drive and Magnus Road.