These stunning images show the latest developments at Bramley-Moore Dock as work continues on Everton's new stadium.
Building work has risen well above the historic walls of the Regent Road site with the concrete work of the four corners visible - showcasing the footprint of the ground. More than 200 workers are in action every day - the most of any time during the project so far. That number will rocket above 1,000 per day during the later stages.
Sections of the steelwork, of which there will eventually be more than 1,000 tonnes, have arrived while four tower cranes will be brought to the dock in the coming weeks.