The new Pamban railway sea bridge being built to connect Mandapam town on the mainland with Rameshwaram on the Pamban Island in Tamil Nadu, may not be ready by November, railway officials said. The bridge is under construction since 2019.
After missing its earlier deadline of March this year, which was later extended to July, railway officials are trying to finish the work by November. “There are 99 horizontal spans of 18.3 metres and one span of 72.5 metres along the length of the bridge. Of the 99 spans, 73 have been laid. Tracks on these spans have been laid too. However, in recent days, wind speed at the project site has increased making it difficult to work at a fast pace,” a senior railway official told The Hindu.
The 72.5-metre span is a “lift-span” or a movable part of the bridge which will rise and let ships pass. “The lift-span has been assembled at the site. It now has to be erected. We need to erect the rest of the 26 spans too,” the official said.