RARE PHOTOS: Our charity could have lost thousands due to thames water delay | Rare Historical Photos

A sign displays the Thames Water logo
A charity’s patience wore rather thin after waiting 18 months for Thames Water to connect a supply. Photograph: Neil Hall/EPA

I work for a charity providing affordable sheltered housing for older people. In January 2024, we began refurbishing a building that was bequeathed to us.

We paid Thames Water to connect a water supply in February 2024. It wasn’t until November that it informed us that it would need permission from Transport for London (TfL) to close part of the road.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.