Central Transmission Utility of India Ltd (CTUIL), a wholly-owned arm of Power Grid Corporation of India Limited has sought for early decision on the allocation of power to the southern States from the Kudankulam Nuclear Power Plant (KKNPP) Units III and IV (1,000 MW each), to plan the transmission system accordingly.
Unit III is expected to be commissioned by May 2025 and Unit-IV is expected to be commissioned by December 2025.
Tamil Nadu being the home State for the KKNPP, has sought for 100% allocation from Unit 3 and 4. Andhra Pradesh, Karnataka, and Telangana have sought for tariff details to finalise their requirements. Puducherry has sought 50 MW, while Kerala has said it does not need any allocation.