Buoyed by the recommendation of MoEF expert committee for grant of environmental clearance to Palamuru-Rangareddy Lift Irrigation Scheme, the project engineers are getting ready to conduct dry run of the Yellur pumping station for first-stage lifting of water soon to pump water into Anjanagiri reservoir at Narlapur and also second-stage lifting at Yedula to pump water into Veeranjaneya reservoir.
According to the project engineers, they have plans to do wet run of at least one pump each at the two pumping stations by the month-end. Since charging of the 60-km 400 KV transmission line from Dindi sub-station to Yedula sub-station was already completed in mid-June, the two pumping station have no power supply issues.
Of the eight and nine pumps of 145 megawatt capacity each to be installed in the two pumping stations, respectively, the irrigation authorities are planning to commission at least 5 pumps each by the year-end. The second pumping station would also have a spare pump of the same capacity.