The Chungthang dam of Sikkim Urja Limited’s 1,200 MW Teesta-III hydroelectric project on river Teesta gave way on October 4, contributing to the death of at least 94 people in the downstream areas of Sikkim and West Bengal. The devastation has refreshed worries over two of three India-assisted, under-construction mega hydropower projects in Bhutan — the 1,200 MW Punatsangchhu Stage-I (Puna-I) and the 1,020 MW Punatsangchhu Stage-II (Puna-II). These projects, along with the 660 MW Kholongchu, are estimated to cost ₹21,637.28 crore, funded by India, benefiting States in northern and eastern India.
Doubts were raised in February 2023, when the Central Electricity Authority (CEA) uploaded a note on the projects completed, being constructed, and pursued under a 2006 agreement on cooperation in the field of hydroelectric power signed between the two countries. The status was updated in August, with hardly any changes.
The CEA note on the Puna-I that was started in 2008 and expected to be commissioned in 2024-25, said: “Project commissioning is being delayed due to movement/subsidence of right bank hill mass in the dam area. Treatment/stabilisation of the right bank and completion of dam work under progress. The option of providing a barrage in the upstream and abandoning of the dam is being studied.”