UNCOVERED: Wet weather added delay to tuebrook leisure centre refurbishment | History Defined

Long-delayed work to refurbish a Liverpool leisure centre has been hit with more setbacks but a date for completion of one of its major flaws has now been confirmed.

After years of waiting, Liverpool Council signed off on work to upgrade and repair the dilapidated Peter Lloyd Lifestyles leisure centre in Tuebrook. An urgent decision was taken by officers in August to green light the pot of cash needed to bring the popular location back into service.

A total of £1.4m has been made available for the work, with more than half - £753,000 - to be used in repairing the roof by contractors Liquid Roofing and Kier building services for project fees. A further £336,000 has been earmarked for “nonessential internal refurbishments” according to the decision report.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.