With Telangana Chief Minister A. Revanth Reddy firm on building the metro rail to the Rajiv Gandhi International Airport (RGIA) at Shamshabad through the Old City from Falaknuma, the focus is definitely on completing the remaining stretch of about 5.5 km from MGBS (Imlibun) to Falaknuma belonging to the first phase of the Hyderabad Metro Rail (HMR) project.
It is easier said than done. After the Majlis Party had successfully stalled the project from being built into the Old City, ostensibly to protect heritage and religious structures when the first phase was being built, the route was in limbo for years, till all of a sudden the previous Bharat Rashtra Samithi (BRS) Government got a re-survey done.
HMR was just about getting ready to issue land acquisition notices to more than 1,000 property owners between MGBS-Falaknmua when this process too did not take off with funds availability being the issue. The Congress Government apparently wants the first leg builder-operator-concessionnaire L&T Metro Rail Hyderabad (L&TMRH) to complete the work but the latter is not prepared to do so pointing out to the ₹5,500 crore loss in the project.